Can you spot the difference?
Even in the pouring rain work continues. In the early part of November, the layer that forms the roof of level -3 and the floor of level -2 was poured. As you can see in both pictures, work is well underway preparing the steel rebar as well as the molds for the walls of level -2. Between the steel rods one can see the openings for stairwell and elevators between the floors.
In the 7 or so hours between the two pictures, cement was poured for the ramp between parking levels -3 and -2 which raps around the southern and western sides of the lot. And lastly, if you look closely in the bottom left hand corner of the pictures, once can see that that work is underway in the back are of the lot which will contain parking on the lower level, and our future auditorium nearer to ground level.